Phase I Water and Sewer Line Improvement Status
(Status subject to change 2-3 business days)
May 1 -16 Installing new waterlines on Avenue Z from 23rd to 30th, on 28th Street from Avenue Z to Westridge Drive, and on Westridge Drive from 28th to 30th.
March 16 Tie-In @ 30th & Westridge (customers within a six block radius on the North side of 30th Street will be affected from 10:00 am to 2:00pm)
March 16 - 18 Pressure test and Pull Bacteria Samples on new lines
May 23 - 31 Tie-in new services (residents will be without water for 1 hour while old services are changed over to new service.)