2500 Block, alley between Avenue R & Q
January 25- Pull Bacteria Samples in the morning (It takes 24 hours to get results)
January 26 &27- Tie-in service (businesses will be without water for approximately 30 minutes while old service lines are changed over to new services)
January 28- Cut and Plug old waterline in the 1700 Block of 26th street
Businesses in the 1800 Block of 26th and 27th street will be out of water from 3:00pm- 4:00pm
37th & Houston Avenue
January 22- Installing 10" T (NO interruptions in service)
The following status is subject to change 2-3 business days:
20th Street/ Avenue K-Q
January 22- Minor construction (mobilization and spotting utility lines)
January 25- February 3- Installing new waterline and services (Starting on Avenue Q)
February 3 & February 4- Tie-in Pressure test and flush(services will be affected)
February 8- Bacteria Samples
February 9 - 12- Tie-in waterline, switch old/new services (Customers will be without water for approximately 4 hours)